Cobra uses the date labeled as TODATE in calendar set 18 to determine the project status date when you set up a project.
As the project advances, you must advance the calendar for each date in the base fiscal calendar until the project concludes. You can change the status date in a calendar by assign the TODATE label to a specific period. You must update the labels and flags simultaneously.
To set the TODATE period:
-
Display the Calendar view of the calendar file that you want to update and select the Calendar Sets tab.
-
In the Select Calendar Set pane, select
Calendar Set 18.
-
In the Calendar Set pane, select the period that you want to tag as the TODATE period and take one of the following actions:
- In the
Calendars group on the Edit tab, click
Set Todate.
- Right-click the period and select
Set Todate on the shortcut menu.
A message displays asking if you want make the selected period the TODATE period.
-
Click
Yes and
on the Quick Access Toolbar to save your changes.